6/2023 Fragment has received final approval and is officially finished! Tenants have moved into most of its 140 apartments and the last remaining units are currently available. The building’s ground floor now offers a wide mix of shops and services, from a cafe and bakery to a restaurant, fitness center, and drugstore. 3. 7. 2023 Read more
5/2023 While the first tenants are already happily living in Fragment, we’re still at work on the finishing touches. Roofs are being covered with greenery, and the common areas are being finalized. Large-format canvases by the graphic artist and painter Petr Kryštůfek are newly on display there. 22. 5. 2023 Read more
2/2023 Svoboda & Williams Rolls Out Next Rental Phase of the Apartments in Fragment 15. 2. 2023 Read more
1/2023 Work is continuing on the building’s interior. We’re finishing up the exterior surfaces and sidewalks, finalizing the preparations for the water elements, and putting the finishing touches on the sculptures. 15. 1. 2023 Read more
10/2022 The iconic Fragment rental apartment building’s big reveal. The supporting monumental sculptures by artist David Černý now installed 1. 10. 2022 Read more
8/2022 In the exterior we have completed the installation of the first sculptures by David Černý. Work on the façade is also continuing. 25. 8. 2022 Read more
7/2022 Intensive interior work continues: we are finishing the carpentry in the apartments, laying tiles, wooden floors, finalizing the installation of equipment. Inside the building, all the professions necessary for the successful completion of the construction are being completed. 15. 7. 2022 Read more
6/2022 Only one month after launching the rent of the apartments in Fragment, demand has been extraordinary. Clients are predominantly interested in the smaller studios, all of which are as of now fully rented out. The larger apartments, especially those with atypical layouts and terraces, are attracting increasing attention. 27. 6. 2022 Read more
5/2022 In the middle of May, we will launch the rent of the apartments in Fragment. The units will be ready in Q1 2023. 10. 5. 2022 Read more
3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more
1/22 Windows are being installed, which are making the first complete areas in the house visible and also allow entrance number 3 to be finished. Interior tempering and HVAC work can now begin. The removal of the massive supporting props is also underway. 7. 1. 2022 Read more
12/2021 The installation of the windows and facades continues, while the upper floors are being concreted under the supervision of Skanska. The building’s first show flat is beginning to take shape. 8. 12. 2021 Read more
11/2021 Sipral windows were installed at the beginning of November and the installer began waterproofing the roof. At the same time, work on the walls between the apartments, the units’ interior partitions, and the basement is ongoing. 1. 11. 2021 Read more
10/2021 The construction of the residential bridge connecting the two wings of the building at the point in which they turn away from each other has been ongoing for the past few weeks. This is a major challenge in terms of structural engineering, but will allow apartments with truly unique interiors to be created. 11. 10. 2021 Read more
8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
2/2021 Fragment’s Foundation Slab and Concrete Pour is Currently Being Prepared 10. 2. 2021 Read more
10/2020 Construction officially commenced on October 1st during the groundbreaking ceremony. 1. 10. 2020 Read more