Warehouse # 1 18. 5. 2022 Share article: Related news 1/2023 Work is continuing on the building’s interior. We’re finishing up the exterior surfaces and sidewalks, finalizing the preparations for the water elements, and putting the finishing touches on the sculptures. 15. 1. 2023 Read more 11/2021 Sipral windows were installed at the beginning of November and the installer began waterproofing the roof. At the same time, work on the walls between the apartments, the units’ interior partitions, and the basement is ongoing. 1. 11. 2021 Read more 5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
1/2023 Work is continuing on the building’s interior. We’re finishing up the exterior surfaces and sidewalks, finalizing the preparations for the water elements, and putting the finishing touches on the sculptures. 15. 1. 2023 Read more
11/2021 Sipral windows were installed at the beginning of November and the installer began waterproofing the roof. At the same time, work on the walls between the apartments, the units’ interior partitions, and the basement is ongoing. 1. 11. 2021 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more